Weekly Work Update

February 26, 2020

What’s happening now (Week of February 24th through February 28th)

  • Installing the dual temp pipe mains in 400 and 410 garages

  • Installing electrical conduits for control wiring in 400 and 410 garages

  • Branch circuiting for mechanical equipment and risers

  • Abatement pre-cleaning of fan coils in 410 Building (see attached detailed schedule)

  • Replacement of Fan Coil equipment serving the 400 Lobby (Fan Coils are in the garage)

  • X-Ray scans in 400 Laundries (X-Ray scans in 410 Laundries complete) (see attached detailed schedule)

  • Pre-cleaning Fan Coils in 410 Building (see attached detailed schedule)

 

Upcoming Work – 3-week look ahead (February 24th through March 13th)

  • Installation activities noted in bullets 1 and 2 above continue until complete

  • Relocate generator in Lower 410 Building – Feb 25-26 (This is a change from February 24th) (Noise rating of 1)

  • Replace roof-Exhaust Fans-start March 2 in 410 Building and March 9 in 400 Building (Noise rating of 1)

  • Remove Boiler #1 in 400 Penthouse-start March 2 (Noise rating of 3)

  • Remove Make-up Air Handler in 410 Penthouse-start Feb 27 (Noise rating of 3)

  • Complete selective demolition of pipe above 410 Community Room and adjacent Toilet Room-start March 2 (Noise rating of 3)

 

Service and Use Interruptions

  • Laundry room closures

    • 400 floors 1-8 Feb 21

    • 400 floors 7-15 Feb 24

    • 400 floors 14-22 Feb 25

    • 400 floors 21-23 Feb 26

    • 410 Laundry Rooms – Floors 1-3 (Scheduled to begin with Floor 1 on Thursday, Feb. 27th); a test will be completed by Gilbert regarding installation of electrical conduit in laundry rooms

    • 400 Lobby for X-ray on first floor – see attached schedule

    • 400 Fitness Room closure for X-ray – see attached schedule

    • 400 Resident Units – recommended vacant for X-rays – see attached schedule

    • Street Closure – Groveland Tentative for Crane at 410 Feb 29 (Saturday)

    • Street Closure – Clifton Tentative for Crane at 400 Mar 7 (Saturday)

    • 400 Office/delivery entrance disruption for ceiling removal – starting Feb 24

    • 410 Community Room and adjacent Toilet Room - TBD

    • 400 Heat off for Boiler #1 removal – 8 hours, Thursday Feb 27

 

*Noise ratings 1 – 5, with 5 being the loudest (jackhammer)

 

 

 

 

Share on Facebook
Share on Twitter
Please reload

Featured Posts

I'm busy working on my blog posts. Watch this space!

Please reload

Recent Posts

July 3, 2020

June 26, 2020

June 19, 2020

June 11, 2020

June 5, 2020

May 29, 2020

May 22, 2020

May 14, 2020

April 30, 2020

Please reload

Archive
Please reload

Search By Tags

I'm busy working on my blog posts. Watch this space!

Please reload

Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square