Installing the dual temp pipe mains in 400 and 410 garages
Installing electrical conduits for control wiring in 400 and 410 garages
Branch circuiting for mechanical equipment and risers
Abatement pre-cleaning of fan coils in 400
Abatement misc. fittings in the 400 garage
Demolition of chilled water system in 410 penthouse (noise rating of 3*)
Upcoming Work – 3-week look ahead
Above installation activities continue
Pre-cleaning Fan Coils in Resident Units (see attached detailed schedule)
New concrete equipment pad in 410 penthouse (noise rating of 3*)
Set new equipment in 400 and 410 penthouses (noise rating of 3*)
X-Ray Laundry room floors in 400 and 410 – start Feb 18
Relocate generator in 410 – start Feb 24
Replace roof top
Exhaust Fans
Ceiling removal
Fan coils serving 400 Lobby (located in garage)
Service and Use Interruptions
Laundry room closures
410 floors 1-8 Feb 18
410 floors 7-15 Feb 19
410 floors 14-20 Feb 20
400 floors 1-8 Feb 21
400 floors 7-15 Feb 24
400 floors 14-22 Feb 25
400 floors 21-23 Feb 26
410 Lobby for X-ray on 1st floor – see attached schedule
410 Community Room closure for X-ray on 20th floor – see attached schedule
400 Lobby for X-ray on first floor – see attached schedule
400 Fitness Room closure for X-ray on 23rd floor – see attached schedule
Resident Units – recommended vacant for X-rays – see attached schedule
Street Closure – Groveland Tentative for Crane at 410 Feb 29 (Saturday)
Street Closure – Clifton Tentative for Crane at 400 Mar 7 (Saturday)
410 Community Room and Adjacent Toilet Room Feb 17
400 Office/delivery entrance disruption for ceiling removal – week of Feb 24
Parking stalls 131, 132, 133 need to be vacant feb 17-21 between 7:00 a.m. and 3:30 p.m.
*Noise ratings 1 – 5, with 5 being the loudest (jackhammer)



Featured Posts
I'm busy working on my blog posts. Watch this space!
Recent Posts
Archive
Search By Tags
I'm busy working on my blog posts. Watch this space!