400 Building Unit Surveys Complete Today

June 29, 2017

The 400 building unit surveys will be complete today.  Beginning tomorrow, June 30, the 410 building unit surveys will start.  The 410 Building Survey schedule is as follows:

 

Friday, June 30 - Floors 20-15

Wednesday, July 5 - Floors 14-9

Thursday, July 6 - Floors 8-3

Friday, July 7 - Floors 2-1 & Make-Up Units

 

As a reminder it is important that we have access to the fan coil unit and its enclosure.  It is requested that all furniture and any other obstructions are moved away from the HVAC equipment/enclosure.  If you have questions about the location of the HVAC equipment please contact the office.

 

If obstructions are present in front of the equipment, Summit House staff members will need to temporarily remove the obstructions for the survey to be completed then move them back; therefore, please have all items moved away so the teams are able to quickly move from unit to unit.

Share on Facebook
Share on Twitter
Please reload

Featured Posts

I'm busy working on my blog posts. Watch this space!

Please reload

Recent Posts

July 3, 2020

June 26, 2020

June 19, 2020

June 11, 2020

June 5, 2020

May 29, 2020

May 22, 2020

May 14, 2020

April 30, 2020

Please reload

Archive
Please reload

Search By Tags

I'm busy working on my blog posts. Watch this space!

Please reload

Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square