February 7, 2020

Summit House Weekly Work Update


What’s happening now


· Installing the dual temp pipe mains in 400 garage
· Installing electrical conduits for control wiring in 400 and 410 garages
· Abatement in the 400 garage
· Conduit runs in Trash Rooms in 400, floors 14-23 (noise r...

May 7, 2019

The Summit House annual meeting will be held on Wednesday, May 8th at 6:30pm, registration beginning at 6:00pm.  There will be an update to the large HIA project at the meeting so you won't want to miss it!  Look here for additional updates following the meeting.

May 7, 2019

Please be informed that as a part of the planning process for HIA, Gilbert Mechanical will need to take a measurement of every floor opening for the HVAC pipes in your HVAC cabinet.  This process will require them to access every unit at Summit House.  

The unit en...

May 7, 2019

The HIA process has been moving along in the background now for over a year.  However, the process is now moving full steam ahead.  Please look for continued updates on this blog as we move forward with the project.

March 26, 2018

Mary Bujold, along with the team of professionals advising the Board on the extensive project known as the HIA project, gave two presentations during the month of March.  The presentations gave updates on the status of the project and made the team available to answer...

February 6, 2018

All Summit House homeowners will be receiving a unit survey asking homeowners if they would like a new HVAC enclosure with the HIA project or replacement of existing materials.  It is imperative that all owners respond to this survey as we must have 100% participation...

September 6, 2017

The HIA Project continues to move forward with both the professional service companies, i.e. engineers as well as with the city planning department.  The design drawings for the various projects within the HIA scope of work are due to CPMI (owner's representative) by S...

July 25, 2017

The Façade Investigation has been rescheduled for Friday, July 28th due to the high wind conditions with the lift machine.  The scope of the rescheduled inspection is as follows:

  • 410 Building-Will be inspected first starting at 9:00 a.m.  The east, south and west si...

July 17, 2017

Scope visual inspections will be July 17th.

Lift visual inspections will be July 25th.  Please no parking in the parking lot at the 410 building from 8:30am until 4:30pm July 25th.

Please see below for an email sent from the engineering firm for further clarification on...

June 29, 2017

The 400 building unit surveys will be complete today.  Beginning tomorrow, June 30, the 410 building unit surveys will start.  The 410 Building Survey schedule is as follows:

Friday, June 30 - Floors 20-15

Wednesday, July 5 - Floors 14-9

Thursday, July 6 - Floors 8-3

...

Please reload

Featured Posts

I'm busy working on my blog posts. Watch this space!

Please reload

Recent Posts

February 7, 2020

September 6, 2017

Please reload

Archive
Please reload

Search By Tags

I'm busy working on my blog posts. Watch this space!

Please reload

Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square